The question a sponsor asks is never “how much did we spend?” but “where will we land?”. This project budget template tracks the budget, the cost so far and a forecast of the final cost, from the time your team already logs in Jira.
Project budget: [Project name]
Owner: [name] · Contract type: [internal / time and materials / fixed price] · Updated: [date]
1. Budget
| Item | Budget |
|---|---|
| Labour | [amount] |
| Other costs | [amount] |
| Contingency | [amount] |
| Total | [amount] |
2. Rates
| Person or role | Cost rate per hour | Billing rate per hour | Valid from |
|---|---|---|---|
| [name] | [rate] | [rate] | [date] |
3. Cost so far
Hours logged in Jira × cost rate = [amount], plus other costs [amount]. Total spent: [amount] ([%] of budget).
4. Forecast
Remaining estimate: [hours] × [average rate] = [amount]. Forecast of the final cost = spent + remaining = [amount]. Variance to budget: [amount, %].
5. Decisions
| Date | Variance | Decision | By |
|---|---|---|---|
| [date] | [amount] | [re-plan / change request / accept] | [name] |
Copied. Paste it into a new Confluence page.
How to use it in Confluence
- Click Copy the template, open a new Confluence page and paste: headings, lists and tables stay as they are.
- Replace the parts in [brackets] and delete what does not apply to you.
- To reuse it, save it as a space template: Space settings › Templates › Create template, then paste.
Keep the forecast honest
- Use real rates with dates. When a rate changes, the old hours keep the old rate.
- Re-estimate the remaining work. The forecast is only as good as the remaining estimate: ask the team, do not subtract hours from the original plan.
- Look at the trend. A forecast that grows a little every week tells you more than any single number.
Related: how to track a project budget in Jira.